Matiri Project | |
---|---|
Country | New Zealand |
Location | Matiri Valley, Tasman District |
Coordinates | 41°39′43″S 172°20′4″E / 41.66194°S 172.33444°E |
Status | Operational |
Commission date | 11 December 2020 |
Owner(s) | Southern Generation Partnership |
Operator(s) | Pioneer Energy |
Thermal power station | |
Primary fuel | Hydropower |
Power generation | |
Nameplate capacity | 4.6 MW |
External links | |
Commons | Related media on Commons |
The Matiri Project is a run-of-river hydroelectric scheme at Lake Matiri and the Matiri River in the South Island of New Zealand. The project takes water from a series of intake weirs at Lake Matiri and pipes it through a 2.4km long buried pipeline to a power station.[1]
The project was originally proposed by New Zealand Energy Limited, which applied for resource consent for a 4.6 MW station in August 2008.[2] The scheme was opposed by environmentalists and kayakers some of whom were angry that the resource consents were not notified nationwide.[3] The proposal was approved and it included a concession granted by the Department of Conservation to build structures on public land. Forest and Bird did not see that there would be any conservation gain in giving the approval.[4]
The development rights were purchased by Pioneer Energy in 2014.[1] Construction began in 2018.[5] Construction was delayed by a slip[6] and by the COVID-19 pandemic, and the scheme was finally commissioned in December 2020.[1] Ownership was transferred to the Southern Generation partnership on completion.[1]
See also
References
- 1 2 3 4 Cherie Sivignon (11 December 2020). "Matiri hydro scheme officially opens near Murchison". Retrieved 1 July 2021.
- ↑ "NZ Energy applies for Matiri Hydro consent". Whitewater NZ. 23 August 2008. Retrieved 1 July 2021.
- ↑ Kidson, Sally (25 September 2008). "Split over Lake Matiri hydro plan". Nelson Mail. Retrieved 30 October 2008.
- ↑ Murdock, Helen (26 May 2011). "DOC's hydro approval damns bats". Nelson Mail. Retrieved 26 May 2011.
- ↑ Ben Bootsma (6 September 2018). "Two new hydro stations coming for the South Island". Stuff. Retrieved 1 July 2021.
- ↑ Cherie Sivignon (22 August 2019). "Moving slip near Murchison forces road closure, impedes work on power project". Stuff. Retrieved 1 July 2021.