The Purple Line is a part of the Namma Metro rail system for the city of Bengaluru, Karnataka, India.[1] As of 2023, the line is 43.49 km (27.02 mi) long and spans 37 stations from Challaghatta in the southwest to Whitefield (Kadugodi) to the east.[2] The Purple Line is mostly elevated, with 31 elevated stations, 5 underground stations and 1 at-grade station. The Line passes through many prime activity centers of the city including Whitefield, Krishnarajapura, MG Road, Vidhana Soudha and Majestic station, which is an interchange station between Purple and Green Lines. Phase I of the Purple Line was the first underground metro section in South India.[3]
Construction
Purple Line sections were opened as indicated below.[4]
History | |||||
---|---|---|---|---|---|
Section | Extension date | Terminal Stations | Length | Stations | |
Reach 1 | 20 Oct 2011 | Baiyappanahalli | M G Road | 6.70 km (4.16 mi) | 06 |
Reach 2 | 16 Nov 2015 | Magadi Road | Mysuru Road | 6.40 km (3.98 mi) | 06 |
UG 1 | 30 Apr 2016 | M G Road | Magadi Road | 5.12 km (3.18 mi)[lower-alpha 1] | 05 |
Reach 1A | 26 Mar 2023 | Krishnarajapura | Whitefield (Kadugodi) | 13.71 km (8.52 mi) [5] | 12 |
Reach 1B[6][7] | 9 Oct 2023 | Baiyappanahalli | Krishnarajapura | 2.10 km (1.30 mi)[8] | 01 |
Reach 2A | 30 Aug 2021 | Mysuru Road | Kengeri | 7.5 km (4.7 mi)[8] | 06 |
Reach 2B | 9 Oct 2023 | Kengeri | Challaghatta | 2.05 km (1.27 mi)[8] | 01 |
Total | Whitefield (Kadugodi) | Challaghatta | 43.49 km (27.02 mi) | 37 |
Phase I
Civil construction work on Phase I of the line began on 15 April 2007 and was originally scheduled to be completed in 5 years. However, the project faced delays and missed several deadlines. Difficult tunnel boring conditions through a mixed geology with hard rock caused major delays.[9][10] The first stretch of Purple Line (Reach 1, fully elevated) between Baiyyappanahalli and Mahatma Gandhi Road was inaugurated on 20 October 2011. Reach 2 (fully elevated) between Mysore Road and Magadi Road commenced operations on 16 November 2015. These two sections operated independently until the final section, the underground stretch between Mahatma Gandhi Road and City Railway station was opened on 30 April 2016, thus linking the previously opened stretches and completing Phase I for the Purple Line.
Costs for the Purple Line were estimated at ₹ 4500–5000 crore. The cost of the underground stretch alone amounted to about ₹ 1000 crores.[11][12] Land acquisition for Phase I of the project cost ₹2,500 crore (US$310 million).[13] BMRCL secured ₹6,500 crore (US$810 million) through long-term loans and ₹300 crore (US$38 million) by selling bonds, while the remaining project cost was funded by Central Government and the State Government. Loans were secured from several agencies - ₹3,000 crore (US$380 million) from the Japan International Cooperation Agency (JICA), ₹600 crore (US$75 million) from the Housing and Urban Development Corporation Limited (HUDCO), ₹25 crore (US$3.1 million) from the Asian Development Bank (ADB), and the rest from a French lending agency. Approximately 10% of the ₹ 6500 crore was to be paid as interest by BMRCL each year. The Federation of Karnataka Chambers of Commerce and Industry (FKCCI) had estimated that interest payment alone would be ₹2 crore (US$250,000). However BMRCL stated that it was not so high but "definitely more than ₹1 crore (US$130,000) per day".[13]".
The tunnels bored using tunnel boring machines (TBMs) are located approximately 60 feet below ground level, have an outer diameter of 6.5 metres and inner diameter of 5.6 metres, and situated are 5 metres apart.[14] Two Japanese TBMs, Helen and Margarita, were used for tunneling work of the Purple Line.[15][16][17][18][19] Tunneling work began in May 2011 and completed in May 2014.[20] Underground stations (City railway station, Sir M Visvesvaraya, Vidhana Soudha and Cubbon Park) were built by cut-and-cover method which required 10,000 controlled blasts using 50,000 kg of explosives of 125 gm gel nitrate capsules due to hard granite rock.[21][22][23] Blasts were carried out daily from 6 am to 7 am from March 2011 to early 2013 (regulations restricted blasting work from being carried out at other times of the day). Preparation for a single blast took approximately 3.5 hours, with the actual duration of a blast being 5 seconds. Approximately, 20,250 truckloads of debris was excavated during construction. Kolar-based National Institute of Rock Mechanics served as consultant for blasting work. There were no injuries during the entire blasting process.[23] A total of 2500 trees were cut down during the construction of both lines of Phase I.[24][25]
Reach 1 was originally scheduled to begin operations in March 2010. After missing several deadlines, it was finally opened to the public on 20 October 2011 at 4 pm IST by Union Urban Development Minister Kamal Nath.[26] There was an overwhelming response to the metro at the commencement of operations. As per BMRCL sources within first three days of operations, 169,019 people used the mass transit system.[27] At the end of the 4th day, about 200,000 passengers had already commuted on Namma Metro. Namma Metro's first 12-day cumulative revenue was ₹10 million (US$130,000).[28] During the first month, about 1,325,000 people traveled by metro.[29] On average, 41,390 people took the train every day, while the average daily revenue was ₹667,262. BMRC earned a revenue of ₹21 million (US$260,000) in its first month of operation.[30] However, average ridership during the first six months of operation was just 24,900 after the initial euphoria. BMRC earned a total of ₹66 million (US$830,000) during the same period.[31] Namma Metro posted a profit of ₹4.1 million (US$51,000) after almost one year of operating Reach I. BMRCL estimates that nearly 8 million passengers traveled on the system during its first year of operations.[32]
Reach 2 received clearance to start services (from Satish Kumar Mittal, Commissioner for Metro Rail Safety - CMRS) on 21 September 2015.[33] Reach 2 was opened to the public on 16 November 2015.[34][35]
BMRCL applied for safety clearance to open the underground stretch in the third week of March 2016.[36] The Commissioner for Railway Safety (CRS) granted clearance to begin operations on the underground section in the first week of April 2016. The underground section was inaugurated by Union Urban Development Minister M. Venkaiah Naidu, Chief Minister Siddaramaiah and other dignitaries at a ceremony at the Vidhana Soudha on 29 April 2016. The inaugural train through the underground section departed from Vidhana Soudha station at 6:35 pm.[37] Namma metro was first driven through the underground section by Loco-pilot Pavithran.[38] The section was opened to the public from 6 am on 30 April 2016.[39][40] Trains ran until 10 pm on the opening day, making 115 trips and transporting about 93,500 passengers, earning BMRCL a revenue of ₹35 lakh (US$44,000).[41][42] The following day, 120 trips were operated on the Purple line, transporting about 125,000 passengers. On the first two days of operation, after opening of the underground section, BMRCL collected over ₹7 million in revenues from the Purple Line.[43][44]
Phase II
In October 2016, the BMRCL began civil work on the west extension of the Purple Line from Mysore Road to Kengeri (8.81 km), later extended to Challaghatta.[45] Construction work on the Purple Line corridor was awarded in two packages for ₹ 660 crore.[46] IL&FS Engineering Construction Company bagged the contract for Reach 2A of 3.94 km (Mysore Road to Pattanagere stretch) that includes four stations at ₹ 327 crore. Soma Enterprise won the contract for Reach 2B of 4.86 km (Pattanagere to Kengeri stretch, later extended to Challaghatta), including two stations and a depot at Challaghatta at ₹ 332 crore. The land needed for the depot at Challaghatta (which is about 1.5 km away from Kengeri station) was already with BMRCL.[45] Later, the line extension included a new station at Challaghatta, close to the depot.[47]
BMRCL floated tenders for the construction of the 15.5-km elevated stretch from Baiyyappanahalli to Whitefield railway station in December 2016. The tenders for Reach 1A and Reach 1B were floated by BMRC on 1 and 6 December respectively.[48] Reach 1A is an 8.03 km section from Baiyyappanahalli to Sitharama Palya (previously Visveshvaraya Ind. Area). The section includes six new stations and is estimated to cost ₹ 670.72 crore. Reach 1B, the 7.21 km section from Kundalahalli to Whitefield, includes seven new stations and is estimated to cost ₹ 666.12 crore. Italian-Thai Development Public Company Limited (ITD) was awarded the contracts for both packages, for a sum of ₹1,300 crore (US$160 million), in May 2017.[49]
Around 270 buildings were demolished for the construction of Reach 1A and 1B. BMRC spent an estimated ₹ 849 crore to acquire properties. Demolition work began in March 2017.[8][50] Construction work began in February 2018.[51]
The extension from Mysore Road to Kengeri in the southwest opened on 30 August 2021 [52] and the extension from Krishnarajapuram to Whitefield(Kadugodi) in the east side opened on 26 March 2023.[53]
Later, Trial Runs began from Baiyappanahalli to Krishnarajapura with one station Benniganahalli in between on 26 July 2023 and from Kengeri to Challaghatta on 29 July 2023. On 9 October 2023, Both the sections were thrown open to the public.
Phase III
The Government of Karnataka planned to extend the purple metro till Malur town in Kolar district Eastwards and Bidadi in Ramanagara district Westwards respectively in Phase 3.
Stations
There are currently 37 stations on the Purple Line. All underground stations were built using the cut-and-cover method. Most underground stations are 300 metres long and 25 metres wide. The interchange station at Majestic is much larger.[21]
Initially, there were no toilets at Namma Metro stations. BMRCL eventually heeded to public demands for toilets and the metro's first toilets were opened at Baiyyappanahalli and Indiranagar stations on 21 June 2013.[54]
In September 2015, it was announced that the proposed Narayanapura metro station would be removed and the proposed Krishnarajapuram metro station would be shifted by 295 metres to the west, due to difficulty in acquiring land in the area.[55] In April 2016, BMRCL revealed that Whitefield metro station, originally proposed to be located 200 metres away from Whitefield railway station, would be shifted so as to be directly opposite the railway station to provide easier connectivity between the metro station and railway station.[13]
Yellow tactile tiles are used at all stations to guide the visually impaired. The tiles start at the ramp and lead to the staircases and lifts.[56]
Purple Line | |||||
---|---|---|---|---|---|
# | Station Name | Opening | Connections /Transits /Terminals | Layout | |
English | Kannada | ||||
1 | Whitefield (Kadugodi) | ವೈಟ್ಫೀಲ್ಡ್ (ಕಾಡುಗೋಡಿ) | 26 March 2023[57] | Whitefield
Kadugodi TTMC |
Elevated |
2 | Hopefarm Channasandra | ಹೋಪ್ ಫಾರ್ಮ್ ಚನ್ನಸಂದ್ರ | 26 March 2023 | Elevated | |
3 | Kadugodi Tree Park | ಕಾಡುಗೋಡಿ ಟ್ರೀ ಪಾರ್ಕ್ | 26 March 2023 | Elevated | |
4 | Pattanduru Agrahara | ಪಟ್ಟಂದೂರು ಅಗ್ರಹಾರ | 26 March 2023 | Elevated | |
5 | Sri Sathya Sai Hospital | ಶ್ರೀ ಸತ್ಯ ಸಾಯಿ ಆಸ್ಪತ್ರೆ | 26 March 2023 | Elevated | |
6 | Nallurhalli | ನಲ್ಲೂರುಹಳ್ಳಿ | 26 March 2023 | Whitefield TTMC | Elevated |
7 | Kundalahalli | ಕುಂದಲಹಳ್ಳಿ | 26 March 2023 | Elevated | |
8 | Seetharamapalya | ಸೀತಾರಾಮ ಪಾಳ್ಯ | 26 March 2023 | Elevated | |
9 | Hoodi | ಹೂಡಿ | 26 March 2023 | Hoodi Halt | Elevated |
10 | Garudacharapalya | ಗರುಡಾಚಾರ್ಪಾಳ್ಯ | 26 March 2023 | Elevated | |
11 | Singayyanapalya | ಸಿಂಗಯ್ಯನಪಾಳ್ಯ | 26 March 2023 | Elevated | |
12 | Krishnarajapura (K.R.Pura) | ಕೃಷ್ಣರಾಜಪುರ (ಕೆ.ಆರ್.ಪುರ) | 26 March 2023 | Blue Line (UC, Ph-2A) | Elevated |
13 | Benniganahalli (Tin Factory) | ಬೆನ್ನಿಗಾನಹಳ್ಳಿ (ಟಿನ್ ಫ್ಯಾಕ್ಟರಿ) | 9 October 2023[58] | Benniganahalli (Planned Suburban Rail Station) | Elevated |
14 | Baiyappanahalli | ಬೈಯ್ಯಪ್ಪನಹಳ್ಳಿ | 20 October 2011 | Baiyyappanahalli | At Grade |
15 | Swami Vivekananda Road | ಸ್ವಾಮಿ ವಿವೇಕಾನಂದ ರಸ್ತೆ | 20 October 2011 | Elevated | |
16 | Indiranagara | ಇಂದಿರಾನಗರ | 20 October 2011 | Elevated | |
17 | Halasuru | ಹಲಸೂರು | 20 October 2011 | Elevated | |
18 | Trinity | ಟ್ರಿನಿಟಿ | 20 October 2011 | Elevated | |
19 | Mahatma Gandhi Road | ಮಹಾತ್ಮಾ ಗಾಂಧಿ ರಸ್ತೆ | 20 October 2011 | Pink Line (Under Construction) | Elevated |
20 | Cubbon Park | ಕಬ್ಬನ್ ಪಾರ್ಕ್ | 30 April 2016 | Underground | |
21 | Dr. BR. Ambedkar Station, Vidhana Soudha | ಡಾ. ಬಿ ಆರ್ ಅಂಬೇಡ್ಕರ್ ನಿಲ್ದಾಣ, ವಿಧಾನ ಸೌಧ | 30 April 2016 | Underground | |
22 | Sir M. Visveshwaraya Station, Central College | ಸರ್ ಎಂ. ವಿಶ್ವೇಶ್ವರಯ್ಯ ನಿಲ್ದಾಣ, ಸೆಂಟ್ರಲ್ ಕಾಲೇಜು | 30 April 2016 | Underground | |
23 | Nadaprabhu Kempegowda station, Majestic | ನಾಡಪ್ರಭು ಕೆಂಪೇಗೌಡ ನಿಲ್ದಾಣ, ಮೆಜೆಸ್ಟಿಕ್ | 30 April 2016 | Green Line | Underground |
24 | Krantivira Sangolli Rayanna Railway Station | ಕ್ರಾಂತಿವೀರ ಸಂಗೊಳ್ಳಿ ರಾಯಣ್ಣ ರೈಲು ನಿಲ್ದಾಣ | 30 April 2016 | KSR Bengaluru City Jn | Underground |
25 | Magadi Road | ಮಾಗಡಿ ರಸ್ತೆ | 16 November 2015 | Elevated | |
26 | Sri Balagangadharanatha Swamiji Station, Hosahalli | ಶ್ರೀ ಬಾಲಗಂಗಾಧರನಾಥ ಸ್ವಾಮೀಜಿ ನಿಲ್ದಾಣ, ಹೊಸಹಳ್ಳಿ | 16 November 2015 | Orange Line (Planned, Phase lll) | Elevated |
27 | Vijayanagara | ವಿಜಯನಗರ | 16 November 2015 | Elevated | |
28 | Attiguppe | ಅತ್ತಿಗುಪ್ಪೆ | 16 November 2015 | Vijayanagara TTMC | Elevated |
29 | Deepanjali Nagara | ದೀಪಾಂಜಲಿನಗರ | 16 November 2015 | Elevated | |
30 | Mysuru Road | ಮೈಸೂರು ರಸ್ತೆ | 16 November 2015 | Orange Line (Planned, Phase lll) | Elevated |
31 | Pantharapalya - Nayandahalli | ಪಂತರಪಾಳ್ಯ - ನಾಯಂಡಹಳ್ಳಿ | 30 August 2021 | Elevated | |
32 | Rajarajeshwari Nagara | ರಾಜರಾಜೇಶ್ವರಿ ನಗರ | 30 August 2021 | Elevated | |
33 | Jnanabharathi | ಜ್ಞಾನಭಾರತಿ | 30 August 2021 | Jnanabharathi | Elevated |
34 | Pattanagere | ಪಟ್ಟಣಗರೆ | 30 August 2021 | Elevated | |
35 | Kengeri Bus Terminal | ಕೆಂಗೇರಿ ಬಸ್ ಟರ್ಮಿನಲ್ | 30 August 2021 | Kengeri TTMC | Elevated |
36 | Kengeri | ಕೆಂಗೇರಿ | 30 August 2021 | Kengeri | Elevated |
37 | Challaghatta | ಚಲ್ಲಘಟ್ಟ | 9 October 2023[59] | Elevated |
Infrastructure
Rolling stock
BMRC procured 150 metro coaches for fifty 3-car train sets in DMC-TC-DMC formation for Phase l of Namma Metro from BEML - Hyundai Rotem at a cost of ₹1,672.50 crore (₹16.72 billion).[60] Coach specifications were as follows: Dimensions: Length-20.8m, Width-2.88m, and Height-3.8m. Each coach has a seating capacity of about 50 and standing capacity of 306 (basis 8 per sqm). Thus, each train had a capacity of about 1000.[61] Traction was through four 180 kW motors in each motor coach. The trains have a maximum speed of 80 km/h and axle load of 15 tonnes. The trains operate on 750V DC with third rail bottom power collector system. Features include stainless steel body fully air-conditioned coaches, longitudinal bank of wide seats, wide vestibules between coaches, non-skid and non-slip floor surfaces, wi-fi enabled, four wide passenger access doors on each side, wide windows, automatic voice announcement system and electronic information and destination display system.
Initial operations on the Purple Line began with twenty-one 3-coach trains. As loads increased with increasing ridership, all trains were converted to six coaches.[62] The first six car train was introduced on the Purple Line on 23 June 2018.[63] The additional coaches were supplied by BEML at a cost of Rs 8.8 crore each.[64]
Traction
Purple Line uses 750 V DC third rail traction.
Signaling
In September 2009, the consortium led by Alstom Project India Limited were awarded a contract worth ₹563.4 crore (US$70.6 million) to supply control and signalling system for the first phase of the project. The consortium is led by Alstom and composed of Alstom Transport SA, Thales Group Portugal S A and Sumitomo Corporation. Alstom will provide the design, manufacture, supply, installing, testing and commissioning of the train control and signalling system and Thales will provide the design, installing, testing and commissioning of the telecommunication system for Phase I of the metro system. It includes the Urbalis 200 Automatic Train Control system which will ensure optimal safety, flexible operations and heightened passenger comfort.[65][66]
The integrated control centre at Baiyyappanahalli has direct communication with trains and stations are CCTV fitted with visual and audio service information.[67]
Operations
Frequency
The metro service runs from 5 am and 12 am daily. The end-to-end travel time on a Purple Line train is 82 minutes.[68] From 7 November 2016, Purple Line trains began running at an interval of every 4 minutes between 9:10 am and 9:58 am to handle rising passenger traffic during morning peak hour.[69] This timing was later withdrawn as the trains were not operating at optimal capacity. From 27 February 2017, the BMRC introduced a new time-table for weekdays. Headway on the line was changed as follows: 4 minutes (08:30-09:10), 7 minutes (07:00-08:30 and 09:10-10:40), 8 minutes (16:00-20:40) and 15 minutes at all other times.[70]
Metro services have occasionally operated beyond 2200 hours. Services are usually extended on festival days or when an international cricket match is held in Bangalore.[71][72]
Speed
The system is designed for a maximum train speed of 80 km/h. However, the Research Design and Standards Organization (RDSO) fixed the speed at which trains are allowed to commercially operate at 67.50 km/h on straight sections, 35 km/h on curves, and 45 km/h in stations.[73] The maximum permitted speed on the underground section is 40 km/h. Purple Line trains usually operate at speeds of 38–40 km/h. According to metro authorities, the trains require more than 400 metres to accelerate from, or decelerate to a halt. As the inter-station distance on the line is about 1 km, the trains have limited time to run at higher speeds.[74]
Fare collection
End-to-end fare on the Purple Line is ₹60 (75¢ US). Commuters who pay using smartcards receive a 5% discount per transaction.
As of April 2016, 37.59% of commuters on the Purple Line use smart cards, while the rest purchase tokens.[75]
Safety
All stations on the line have 4 emergency exits, and Majestic station has 18 emergency exits. Stations have been built to withstand zone III earthquakes. Bangalore is located in a zone II earthquake area. The tunnels are equipped with walkways to enable passengers to disembark from a train and walk to the nearest station in case of a technical failure. The underground section is also equipped with 5 cross-passages that will enable passengers to move between tunnels, in case a tunnel section fills up with smoke. There are three tunnel cross-passages between Majestic and Sir M Visvesvaraya metro station, and one each between Vidhana Soudha and Central College, and Majestic and City Railway station. All stations were built with flame retardant materials, and also have 100,000 litres of water stored on-site for use in case of a fire.[76]
See also
Notes
- ↑ The stretch from M. G. Road to Magadi Road is 5.12 km (3.18 mi). UG 1 is the name given by the BMRCL to the underground portion of this stretch, which is composed of two 4.82 km (3.00 mi) tunnels.
References
- ↑ "Whitefield line boosts Bengaluru Metro's average daily ridership by 80K; cuts traffic congestion by 14%".
- ↑ "Bengaluru: 7 new Metro trains to ensure frequency after operations begin on Kengeri line | Bengaluru News - Times of India". The Times of India. 20 August 2021.
- ↑ "You can take underground metro from April 30". The Hindu. 25 April 2016. Retrieved 25 April 2016.
- ↑ "Metro Network". www.bmrc.co.in. Archived from the original on 14 August 2015. Retrieved 26 April 2016.
- ↑ "PM inaugurates much-awaited Whitefield Metro line in Bengaluru". Deccan Herald. 25 March 2023. Retrieved 26 March 2023.
- ↑ "Baiyappanahalli-Whitefield line may be ready by Dec-end". The New Indian Express. Retrieved 15 May 2022.
- ↑ "Bengaluru Metro blames rain for delay of Baiyappanahalli-Whitefield trial run". The Indian Express. 21 September 2022. Retrieved 24 September 2022.
- 1 2 3 4 "BMRCL begins razing structures for metro to Whitefield". Bangalore Mirror. Retrieved 4 April 2017.
- ↑ "Hard rock beaten on Bangalore slurry drives". www.tunneltalk.com. Retrieved 5 September 2020.
- ↑ "Getting Bangalore Metro north-south line back on track". www.tunneltalk.com. Retrieved 5 September 2020.
- ↑ "Bangalore underground metro section inaugurated". The Indian Express. 30 April 2016. Retrieved 29 April 2016.
- ↑ "Metro ready but how do we get to the station?". Deccan Herald. 27 April 2016. Retrieved 27 April 2016.
- 1 2 3 "Metro June Deadline Stands, But With Rider". The New Indian Express. 20 January 2016. Retrieved 27 April 2016.
- ↑ "15 Trains to Run at Frequency of 10 Minutes on Metro's Purple Line". The New Indian Express. Retrieved 27 April 2016.
- ↑ "Bengaluru Metro Goes Underground - With Help From Helen And Margarita". NDTV.com. Retrieved 28 April 2016.
- ↑ Special Correspondent (28 September 2012). "A smoother passage for Margarita". The Hindu. Chennai, India. Retrieved 4 March 2013.
- ↑ Bangalore, 23 Sep 2012, DHNS (23 September 2012). "Tunnelling along north-south corridor to begin soon". Deccan Herald. Retrieved 4 March 2013.
{{cite web}}
: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link) - ↑ Update : 06:47 pm IST (18 December 2012). "Metro rushes to meet deadline". Deccan Chronicle. Retrieved 4 March 2013.
{{cite web}}
: CS1 maint: numeric names: authors list (link) - ↑ Bangalore, 21 Feb 2013, DHNS (21 February 2013). "After Helen, Margarita, it's Krishna and Kaveri". Deccan Herald. Retrieved 4 March 2013.
{{cite web}}
: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link) - ↑ "Namma Metro fare more than Delhi Metro - Bangalore Mirror -". Bangalore Mirror. Retrieved 26 April 2016.
- 1 2 "Conducted 10,000 blasts to cut hard rocks: BMRCL". Deccan Herald. Retrieved 26 April 2016.
- ↑ Krishnan, Raghu. "Phase one of Bengaluru Metro to be launched today". Business Standard. Retrieved 28 April 2016.
- 1 2 "10,000 Blasts, 0 Injuries: Metro's Historic Run Today". The New Indian Express. Retrieved 29 April 2016.
- ↑ "Lessons from phase 1: Can Bengaluru Metro beat deadline blues in underground trail? - Firstpost". Firstpost. 27 April 2016. Retrieved 27 April 2016.
- ↑ "Underground Bengaluru Metro Station service flagged off, Siddaramaiah seeks Centre's help for Namma Metro phase III | Latest News & Updates at Daily News & Analysis". dna. 29 April 2016. Retrieved 29 April 2016.
- ↑ "Metro comes to Bangalore finally". The Times of India. 20 October 2011.
- ↑ "Revenue Services Report" (PDF). Archived from the original (PDF) on 24 June 2013.
- ↑ Madhumathi D.S. "Business Line : Industry & Economy / Logistics : Namma Metro rides on 'gawk' power". Business Line. Retrieved 3 January 2012.
- ↑ "13.25 lakh rode the Metro". The Times of India. 25 November 2011. Archived from the original on 15 July 2012.
- ↑ "Namma Metro gains momentum – southindia – Bangalore – ibnlive". Ibnlive.in.com. Archived from the original on 23 November 2011. Retrieved 3 January 2012.
- ↑ "Joyrides in Bangalore Metro are over – Bangalore – DNA". Daily News and Analysis. Retrieved 25 July 2012.
- ↑ "Bangalore Metro posts Rs 41 lakh profit in first year – Bangalore – DNA". Daily News and Analysis. 18 October 2012. Retrieved 18 October 2012.
- ↑ Express News Service (20 September 2015). "Mysore Road-Magadi Road Metro Stretch Gets Nod". The New Indian Express.
- ↑ Maya Sharma (16 November 2015). "Bengaluru Starts Metro Services Between Magadi Road, Mysuru Road". NDTV.com. Retrieved 18 November 2015.
- ↑ Preeti Panwar. "Bengaluru: Namma Metro Magadi Road-Mysuru Road line inaugurated". oneindia.com. Retrieved 18 November 2015.
- ↑ "South India's first UG metro launched in Bengaluru on Friday - Times of India". The Times of India. 24 April 2016. Retrieved 25 April 2016.
- ↑ "CM Launches Namma Metro Underground Corridor Train in Vidhana Soudha". The New Indian Express. Retrieved 29 April 2016.
- ↑ "Namma Bengaluru is now a truly metropolitan city - Bangalore Mirror -". Bangalore Mirror. Retrieved 29 April 2016.
- ↑ "Baiyappanahalli-Nayandahalli metro opens on April 30 - Bangalore Mirror -". Bangalore Mirror. Retrieved 25 April 2016.
- ↑ "Bangaloreans cheer as Namma Metro rolls on underground tracks - Firstpost". Firstpost. 30 April 2016. Retrieved 30 April 2016.
- ↑ "Bengalureans enjoy date with east-west corridor". Deccan Herald. May 2016. Retrieved 1 May 2016.
- ↑ "For First Metro Rider, It Feels Like Good Old Days". The New Indian Express. Retrieved 1 May 2016.
- ↑ "Bengalureans go purple with Namma Metro". Deccan Herald. Retrieved 1 May 2016.
- ↑ "Record one lakh commuters travel in Bengaluru metro on Sunday". India.com. 2 May 2016. Retrieved 1 May 2016.
- 1 2 "BMRCL hints at extending Purple Line up to Challaghatta depot near Kengeri". Deccan Herald. 5 December 2016. Retrieved 3 January 2017.
- ↑ "BMRCL invites bids for 3-km extension from Nagasandra". Deccan Herald. 13 October 2016. Retrieved 5 November 2016.
- ↑ "Challaghatta residents lucky to get Bengaluru Metro connectivity thanks to land crunch at Kengeri". The New Indian Express. Retrieved 31 August 2021.
- ↑ "BMRCL floats another tender for civil work on Whitefield corridor". Deccan Herald. 7 December 2016. Retrieved 7 March 2017.
- ↑ Menezes, Naveen. "Italian firm ITD to Build Byappanahalli-Whitefield metro stretch". The Economic Times. Retrieved 3 May 2017.
- ↑ "Building demolition in progress for Whitefield Metro line". Deccan Herald. 4 April 2017. Retrieved 4 April 2017.
- ↑ Staff Reporter (10 December 2016). "Electronics City inches closer to being on metro map". The Hindu. Retrieved 11 December 2016.
- ↑ "Namma Metro adds 6 stations to Purple Line". The Hindu. 29 August 2021. ISSN 0971-751X. Retrieved 31 August 2021.
- ↑ "Whitefield (Kadugodi) to Krishnarajapura Metro Line: Route, fare, map other details". TimesNow. 25 March 2023. Retrieved 26 March 2023.
- ↑ "At Metro, wanna pee? Pay Rs 3 - Bangalore". Daily News and Analysis. Retrieved 28 September 2013.
- ↑ Lalitha, S. (25 September 2015). "Namma Metro Phase II to be Realigned at 2 Stations". The New Indian Express.
- ↑ G. Ananthakrishnan (14 January 2013). "Linking modes of commute". The Hindu. Chennai, India. Retrieved 4 March 2013.
- ↑ "Namma Metro: Wait for K.R. Puram to Whitefield line almost over; services to start from March 26". TimesNow. 20 March 2023. Retrieved 20 March 2023.
- ↑ "Bengaluru Metro: Whitefield-Challaghatta Line Opening in August - TimesProperty". timesproperty.com. Retrieved 18 July 2023.
- ↑ "Challaghatta residents lucky to get Bengaluru Metro connectivity thanks to land crunch at Kengeri- The New Indian Express".
- ↑ "BEML bags Rs 1,672-cr Metro Rail order". www.rediff.com. Retrieved 6 September 2020.
- ↑ "Train Every 3 Minutes Also Possible". The New Indian Express. Retrieved 28 April 2016.
- ↑ "All 42 trains now have 6 coaches".
- ↑ "Second six-coach Namma Metro train flagged off - Times of India". The Times of India. 4 October 2018. Retrieved 24 January 2019.
- ↑ "Bengaluru: Six-coach trains to double capacity of Namma Metro". The Week. Retrieved 6 September 2020.
- ↑ "Alstom will provide train control and signalling system for the new Bangalore metro network in India". Alstom. Retrieved 2 October 2011.
- ↑ "Alstom-led consortium in pact with Bangalore Metro". Business Standard. 18 September 2009. Retrieved 3 May 2010.
- ↑ "NAMMA-METRO-IS-A-GEEK-TRAIN". The Times of India. 16 October 2011. Retrieved 21 October 2011.
- ↑ "Get ready to crisscross Bengaluru in 33 mins - Times of India". The Times of India. 27 April 2016. Retrieved 27 April 2016.
- ↑ "sampige road-puttenahalli: BMRC hoping to finish work on Sampige Road-Puttenahalli line ahead of April 2017 deadline | Bengaluru News". The Times of India. 5 November 2016. Retrieved 20 December 2020.
- ↑ Staff Reporter (28 February 2017). "Passengers welcome higher Namma Metro frequency". The Hindu. ISSN 0971-751X. Retrieved 6 September 2020.
- ↑ Bangalore, 22 Dec 2012, DHNS (22 December 2012). "Bar timings relaxed for revellers". Deccan Herald. Retrieved 6 June 2013.
{{cite web}}
: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link) - ↑ "Metro to run till midnight today, tomorrow". The Times of India. 24 December 2012. Archived from the original on 26 January 2013. Retrieved 6 June 2013.
- ↑ Chethan Kumar, Bangalore, 22 May 2013, DHNS (22 May 2013). "RDSO in no hurry to allow Metro to up speed". Deccan Herald. Retrieved 6 June 2013.
{{cite web}}
: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link) - ↑ "Metro to run at 40 km per hour on underground section". Deccan Herald. Retrieved 27 April 2016.
- ↑ Suchith Kidiyoor (13 April 2016). "Metro on a smartcard roll". bangaloremirror.indiatimes.com. Retrieved 20 December 2020.
- ↑ "From today, Metro's on a roll; it's safe too - Bangalore Mirror -". Bangalore Mirror. Retrieved 28 April 2016.
External links
Media related to Purple Line (Namma Metro) at Wikimedia Commons