Solar power in Gujarat, a state of India, is a fast developing industry given that the large state is mostly arid. It was one of the first states to develop solar generation capacity in India.

As of 31 March 2022, total installed solar power generation capacity of the state was 7,180 MW.[1]

State solar policy

As of 30th of June 2022, Gujarat has an installed capacity of 19,414 MW of renewable energy, and includes 9419.42 MW of wind power, 7806.80 MW of solar power, 1990 MW of large hydro power, 109.26 MW of bio power and 89.39 MW from small hydro power.[2]

Under the Scheme for Development of solar parks and Ultra-mega Solar Power Projects is underway with a target of setting up to 40,000 MW of Solar capacity.[2]

In addition to the existing solar power policy, the state has also come out with a solar-wind hybrid policy, looking to establish four-five such parks with at least 2000 MW capacity.[3]

Total installed solar power generation capacity of the state increased from 4,431 MW in March 2021[4] to 7,180 MW in March 2022.[1]

Rooftop solar

As of 30 June 2021, Gujarat has a total installed rooftop solar capacity of 1.27 GW with more than 2 lakh homes with installations.[5] Gujarat is a top performing state in India in respect to rooftop solar.[6]

Location of Solar parks

Solar power plants across the state[7][8]
Location District Site co-ordinates Nominal Power (MWp) Production
(Annual GW·h)
Developer Notes
Bhersam Bharuch 21°46′12.5″N 72°50′26.0″E / 21.770139°N 72.840556°E / 21.770139; 72.840556 6 - KPI Green Energy
Khavda Kachchh 24°02′15.1″N 69°32′28.6″E / 24.037528°N 69.541278°E / 24.037528; 69.541278 240 - KPI Green Energy
Ora Bharuch 21°51′23.2″N 72°53′18.1″E / 21.856444°N 72.888361°E / 21.856444; 72.888361 30 - KPI Green Energy
Ochhan Bharuch 21°59′14.7″N 73°02′00.5″E / 21.987417°N 73.033472°E / 21.987417; 73.033472 17 - KPI Green Energy
Sarod Bharuch 22°09′49.7″N 72°44′39.0″E / 22.163806°N 72.744167°E / 22.163806; 72.744167 16 - KPI Green Energy
Samoj Bharuch 22°09′06.8″N 72°43′41.4″E / 22.151889°N 72.728167°E / 22.151889; 72.728167 56 - KPI Green Energy
Shahpura Bharuch 21°52′28.2″N 73°06′32.0″E / 21.874500°N 73.108889°E / 21.874500; 73.108889 19.8 - KPI Green Energy
Bhensali Bharuch 21°43′13.6″N 72°44′46.9″E / 21.720444°N 72.746361°E / 21.720444; 72.746361 5.2 - KPI Green Energy
Jhanor Bharuch 21°50′8.8″N 73°07′01.6″E / 21.835778°N 73.117111°E / 21.835778; 73.117111 2.7 - KPI Green Energy
Tanchha Bharuch 21°53′50.9″N 72°54′11.3″E / 21.897472°N 72.903139°E / 21.897472; 72.903139 17 - KPI Green Energy
Vagra Bharuch 21°50′16.3″N 72°50′34.7″E / 21.837861°N 72.842972°E / 21.837861; 72.842972 10.5 - KPI Green Energy
Muler Bharuch 21°52′23.5″N 72°40′49.5″E / 21.873194°N 72.680417°E / 21.873194; 72.680417 9.9 - KPI Green Energy
Kurchan Bharuch 21°54′23.8″N 72°57′53.0″E / 21.906611°N 72.964722°E / 21.906611; 72.964722 18 - KPI Green Energy
Vedcha Bharuch 22°00′32.7″N 72°56′32.2″E / 22.009083°N 72.942278°E / 22.009083; 72.942278 21.5 - KPI Green Energy
Sudi Bharuch 21°53′30″N 72°53′55″E / 21.89167°N 72.89861°E / 21.89167; 72.89861 100 - KPI Green Energy
JafrabadAmreli20°52′34″N 71°16′57″E / 20.87611°N 71.28250°E / 20.87611; 71.28250 (Jafrabad Solar Park)58.322Sunkon Energy[9]
WadgamAnand22°19′12″N 72°25′48″E / 22.32000°N 72.43000°E / 22.32000; 72.43000 (Wadgam Solar Park)1525.846Acme Tele Power
IsanpurAnand22°28′51″N 72°31′25″E / 22.48083°N 72.52361°E / 22.48083; 72.52361 (Isanpur Solar Park)11.533Harsha Engineers
Gunthawada[10][11][12][13]Banaskantha23°55′07″N 71°56′28″E / 23.91861°N 71.94111°E / 23.91861; 71.94111 (Precious Solar Park)[14]15.226.28Precious (Moser Baer)Commissioned 11 October 2011
Gunthawada[10][11][12][13]Banaskantha23°54′40″N 71°55′52″E / 23.91111°N 71.93111°E / 23.91111; 71.93111 (Solitaire Solar Park)[14]1525.9Solitaire (Moser Baer)Commissioned 11 October 2011, with Precious cost Rs 465 crore, area 305 acre, 236,000 Thin Film modules[15]
DhaneraBanaskantha24°31′27″N 72°12′12″E / 24.52417°N 72.20333°E / 24.52417; 72.20333 (Dhanera Solar Park)2545.377Sand Land Real Estate
Bharuch1MBH Power
Gandhinagar1GSEC-TPS
Gandhinagar1PDPU-GPCL-GEDA250 kW from Thin-Film, 750 kW from Poly-crystalline solar cells.
MithapurJamnagar22°36′N 72°07′E / 22.600°N 72.117°E / 22.600; 72.117 (Mithapur Solar Power Plant)25.0Tata PowerCommissioned 25 January 2012
ShilojJunagadh22°49′09″N 71°00′32″E / 22.81917°N 71.00889°E / 22.81917; 71.00889 (Mithapur Solar Power Plant)[16]1019.585Mono Steel SolarOutput decreases 0.7%/year from 20 GWh
Bitta[17]Kutch23°15′46″N 69°01′27″E / 23.26278°N 69.02417°E / 23.26278; 69.02417 (Bitta Solar Park)[18]40.066.576Adani PowerCompleted January 2012 using 400,000 modules.[19] Completed in 150 days at a cost of Rs 400 crore.[20] (6760 million INR) 100 MW planned
ShivlakhaKutch5Backbone
BhujKutch1Essar Power
PanandhroKutch5GMDC
PratapgarhKutch23°21′59″N 70°44′41″E / 23.36639°N 70.74472°E / 23.36639; 70.74472 (Pratapgarh Solar Park)[21]913.451Integrated Coal Mining (ICML)0.5 MW Amorphous Si, 0.5 MW CdTe, 8 MW Crystalline Si
ShivlakhaKutch23°21′54″N 70°37′26″E / 23.36500°N 70.62389°E / 23.36500; 70.62389 (Konark Solar Park)[22]58.87Konark GujaratVikram Solar
ShivlakhaKutch23°19′28″N 70°24′01″E / 23.32444°N 70.40028°E / 23.32444; 70.40028 (Shivlakha Solar Park)[23]2030.835Solar Semiconductor
KarmariaKutch23°12′34″N 70°13′56″E / 23.20944°N 70.23222°E / 23.20944; 70.23222 (Karmaria Solar Park)[24]15.40121.108Sun BorneSolar World SW-230, cost 2102 million Rs, output is derated 1%/year
KhirsaraKutch23°21′32″N 70°03′14″E / 23.35889°N 70.05389°E / 23.35889; 70.05389 (Khirsara Solar Park)[25]58.147Unity PowerSF-145-L 145Wp Copper Indium Selenide
KhirsaraKutch23°21′37″N 70°03′15″E / 23.36028°N 70.05417°E / 23.36028; 70.05417 (Welspun Solar Park)15Welspun Urja Gujarat
Narmada Canal - ChandrasanMehsana1GSEC-Canal
CharankaPatan213.9Consists of 31 projectsCommissioned 19 April 2012
Patan5Jaihind Projects
BhadradaPatan23°40′57″N 71°46′30″E / 23.68250°N 71.77500°E / 23.68250; 71.77500 (Bhadrada Solar Park)5.0017.963Lanco Solar21,740 230 Wp Poly Si panels
ChadiyanaPatan23°41′32″N 71°34′01″E / 23.69222°N 71.56694°E / 23.69222; 71.56694 (Chadiyana Solar Park)1523.955Lanco Solar5 MW from 20,647 230W Poly Silicon and 2,464 102W thin film; 10 MW from multi crystalline Si 230W and 235W panels[26]
DahisarPatan20PLG Photovoltaic
HilabeliPorbandar21°57′24″N 71°19′44″E / 21.95667°N 71.32889°E / 21.95667; 71.32889 (Hilabeli Solar Park)1017GHI Energyfixed tilt mounted at 20° angle[27]
Kerala & BapodarPorbandar21°37′39″N 69°49′57″E / 21.62750°N 69.83250°E / 21.62750; 69.83250 (Kerala & Bapodar Solar Park)[28]2035.425Hiraco Renewable Energy
BapodarPorbandar21°37′39″N 69°49′57″E / 21.62750°N 69.83250°E / 21.62750; 69.83250 (Bapodar Solar Park)1527.265Moser Baer125,100 80W First Solar and 13,490 370W MBSL panels, 18 880 kW Sunny Central SMA-800 inverters
DhankRajkot21°46′17″N 70°05′04″E / 21.77139°N 70.08444°E / 21.77139; 70.08444 (APCA Power Solar Park)58.699APCA Power
DhankRajkot21°46′35″N 70°04′47″E / 21.77639°N 70.07972°E / 21.77639; 70.07972 (Aravali Solar Park)[29]58.02Aravali Infrapower
DhankRajkot21°43′56″N 70°06′07″E / 21.73222°N 70.10194°E / 21.73222; 70.10194 (Dhank Solar Park)[30]1017.678CBC Solar
DhankRajkot21°43′56″N 70°06′07″E / 21.73222°N 70.10194°E / 21.73222; 70.10194 (Ganeshvani Solar Park)[31]58.839Ganeshvani Merchandise
Mervadar and DhankRajkot21°43′56″N 70°06′07″E / 21.73222°N 70.10194°E / 21.73222; 70.10194 (Ganges Solar Park)15Ganges Entertainment
MervadarRajkot21°44′11″N 70°07′12″E / 21.73639°N 70.12000°E / 21.73639; 70.12000 (Mervadar Solar Park)[32]1017.835GreenInfra[33]Cost Rs 130 crore, First Solar thin film
BhatkotaSabarkantha23°33′35″N 73°17′08″E / 23.55972°N 73.28556°E / 23.55972; 73.28556 (Abellon Solar Park)3Abellon CleanenergyConstructed by Waaree Energies Ltd.
KhadodaSabarkantha22°52′39″N 72°04′13″E / 22.87750°N 72.07028°E / 22.87750; 72.07028 (Khadoda Solar Park)10.2Azure Power (Haryana)
Nani NaroliSurat21°25′20″N 73°07′30″E / 21.42222°N 73.12500°E / 21.42222; 73.12500 (Nani Naroli Solar Park)57.53GIPCL
DhamaSurendranagar23°12′N 71°24′E / 23.200°N 71.400°E / 23.200; 71.400 (Dhama Solar Park)58.537Azure Power
FatepurSurendranagar23°23′57″N 71°38′20″E / 23.39917°N 71.63889°E / 23.39917; 71.63889 (Fatepur Solar Park)58EMCOoutput declines 0.7%/year
FatepurSurendranagar23°25′05″N 71°37′20″E / 23.41806°N 71.62222°E / 23.41806; 71.62222 (Mi My Solar Park)1524.873Mi My[34]
DhamaSurendranagar23°24′N 71°42′E / 23.400°N 71.700°E / 23.400; 71.700 (Dhama Solar Park)5Environmental System
SujangadhSurendranagar22°43′35.77″N 71°25′58.16″E / 22.7266028°N 71.4328222°E / 22.7266028; 71.4328222 (Sujangadh Solar Park)25Louroux Bio Energies
DhamaSurendranagar23°30′N 71°42′E / 23.500°N 71.700°E / 23.500; 71.700 (Dhama Solar Park)9.2720.498Millennium Synergyoutput declines 0.5%/year
PatdiSurendranagar23°09′N 71°45′E / 23.150°N 71.750°E / 23.150; 71.750 (Patdi Solar Park)11.815Rajesh Power Services
PatdiSurendranagar1Rasna Marketing Services
Surendranagar1Som Shiva
SurelSurendranagar23°28′12″N 71°35′06″E / 23.47000°N 71.58500°E / 23.47000; 71.58500 (Surel Solar Park)2535.41Visual Percept Solar ProjectsCommissioned 31 December 2011, cost 138 million INR/MW
Tikar[35]Surendranagar23°09′N 71°06′E / 23.150°N 71.100°E / 23.150; 71.100 (Tikar Solar Park)10.2216.82Waa Solar (Madhav Power)First Solar Thin Film CdTe Solar Modules, Commissioned December 2011
Total 702.30[36][37][38]1095 (est)

Solar Power Generation Report Statewide

Source: SLDC Gujarat[39]

2011 Generation detail

2012 Generation detail

2013 Generation detail

2014 Generation detail

2015 Generation detail

2016 Generation detail

Project list

Source: GEDA[88]

Gujarat Solar Park-1

Gujarat solar park 1, also called Charanka Solar Park, is being built on a 2,000-hectare (4,900-acre) plot of land near Charanka village in Patan district, northern Gujarat. So far, the park has witnessed investments of Rs 5,365 crore and generated 3,441 million units till date.

Installed generation capacity is at about 615 MW at present, having been commissioned by 31 developers in the Solar Park. GACL (Gujarat Alkalies and Chemicals Limited) is setting up 30 MW Solar PV plant, and GNFC (Gujarat Narmada Valley Fertilizers and Chemicals) is in the process of setting up 10 MW project.

The Gujarat Power Corporation Limited (GPCL), the project's developer, said in April, 2018 that further capacity addition of 150 MW taking the total to 790 MW may be opted for soon given the availability of land in the Park.[89]

Projects of 95MW are under construction and 30MW under planning as of December, 2018.[90]

See also

References

  1. 1 2 Balachandar, G. (19 April 2022). "Renewable capacity addition: Rajasthan and Gujarat pip Tamil Nadu and Karnataka". The Hindu Businessline. Retrieved 30 May 2022. (subscription required)
  2. 1 2 "Gujarat's Total Renewable Energy Installed Capacity stands at 19,415 MW". DeshGujarat. 20 July 2022. Retrieved 18 September 2022.
  3. "Gujarat riding on the suns chariot". Times of India. 2 December 2018. Retrieved 25 January 2019.
  4. Dave, Kapil; Damor, Kalpesh (7 July 2021). "Green leap: Gujarat set for 3-fold RE surge". The Times of India. Retrieved 21 September 2021.
  5. Shukla, Harsh (6 October 2021). "Gujarat's Residential Rooftop Solar Program Extended to 750 MW from 600 MW". Mercom India. Retrieved 4 December 2021.
  6. "Gujarat is progressing towards its solar PV rooftop target 2021-22". pv magazine India. Retrieved 4 December 2021.
  7. Gujarat Solar Power Plants
  8. Solar PV Plants Commissioned in Gujarat
  9. Solar power project in Gujarat, India
  10. 1 2 Solar power plant in Ahmedabad Asia's biggest
  11. 1 2 Moser Baer Clean Energy Limited commissions largest solar power capacity
  12. 1 2 Gunthawada, India
  13. 1 2 15MWp Solar PV Power Project in Village Gunthavada (Dalpatpura), Taluk Kankarej, District-Banaskantha, Gujarat State, India
  14. 1 2 PDD
  15. Moser Baer commissions 30-MW solar farm in Gujarat
  16. PDD
  17. Adani Power to invest Rs 3,000 cr in solar power
  18. PDD
  19. Adani Group commissions largest solar power project
  20. Adani commissions Rs 400 cr 40 mw solar unit in Gujarat
  21. PDD
  22. PDD
  23. PDD
  24. PDD
  25. PDD
  26. PDD Chadiyana
  27. GHI PDD
  28. Hiraco PDD
  29. 1 2 PDD
  30. PDD
  31. PDD
  32. PDD
  33. Operational Projects
  34. Solar PV Power Project by MMPL in Fatepur, Gujarat
  35. Surendranagar Solar Farm
  36. Installed Capacity
  37. Solar Park Day 1 Highlights
  38. Installed Capacity
  39. Energy Account Archived 8 June 2012 at the Wayback Machine
  40. New Solar Project by Abellon Clean Energy Ltd
  41. New Solar Project by Acme Solar Technologies (Gujarat) Pvt. Ltd
  42. Adani Group commissions 40mw solar power plant in Gujarat
  43. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 PV India Map
  44. PDD
  45. Project Portfolio
  46. Avatar Solar Receives 5 MW Indian Project Contract
  47. Solar Power (shiv Lakhash) by Backbone Enterprises Ltd
  48. Tata Power commissions 25 MW solar project in Gujarat
  49. New Solar Project by Claris Lifesciences Ltd
  50. Proposal for construction
  51. New Solar Power Project by Emco Ltd
  52. New Solar Project by Esp Urja Pvt Ltd
  53. Essar Power commissions 1MW solar photovoltaic plant in Bhuj
  54. New Solar Power Project by Ganges Green Energy Pvt Ltd
  55. New Solar Project by Ghi Energy Pvt. Ltd
  56. 1 2 3 Lanco Infra completes 56 MW grid connected solar photovoltaic power plants in Gujarat
  57. Dedication of 5 MW Solar Power Plant to the Nation
  58. GMDC to set up 5MW solar plant
  59. New Solar Project by Hiraco Renewable Energy Pvt Ltd
  60. New Solar Project by India Solar Ray Power Pvt Ltd
  61. New Solar Power Project by Industrial Power Infrastructure Ltd
  62. New Solar Project by Integrated Coal Mining Ltd
  63. Project Overview
  64. New Solar Project by Kemrock Renewable Energy Ltd
  65. New Solar Project by Konark Gujarat Pv Pvt Ltd
  66. Towards 25 years of carbon-free power
  67. PDD
  68. Martifer Solar, Louroux Bio Energies to collaborate on 25MW of solar projects in Gujarat, India
  69. Solar Photovoltaic Power Project by Louroux Bio Energies Ltd
  70. Electricity Projects
  71. New Solar Project by Millenium Synergy Gujarat Pvt Ltd
  72. Solar Power (una) by Mono Steel India Ltd
  73. New Solar Project by Moser Baer Energy And Development Ltd
  74. New Solar Power Project by Plg Photovoltaic Ltd
  75. Solar Power (patdi) by Rasna Marketing Services LLP
  76. New Solar Power Project by Responsive Sutip Ltd
  77. Our Projects
  78. New Solar Project by Sandland Real Estates Pvt Ltd
  79. New Solar Project by Som Shiva (Impex) Ltd
  80. SunEdison Announces Activation of 25MW Solar Power Plant in Asia’s Largest Solar Park in Gujarat, India
  81. 25MW Solar Plant Opens in Asia's Largest Solar Park
  82. SunBorne Energy pools funds for Gujarat solar plant
  83. SunBorne Energy achieves financial closure for 15-MW solar plant
  84. New Solar Power Project by Ujjawala Power Pvt Ltd
  85. New Solar Project by Visual Percept Solar Projects Pvt Ltd
  86. New Solar Power Project by Yantra E Solar India Pvt Ltd
  87. New Solar Project by Zeba Solar North Pvt Ltd
  88. Details of Solar Power Project Project Developers
  89. "Solar power capacity at Charanka Solar Park to touch 790 MW". DNA. 21 April 2018. Retrieved 25 January 2019.
  90. "Gujarat riding on the suns chariot". Times of India. 2 December 2018. Retrieved 25 January 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.