Lower Granite Dam
View from the northwest
Lower Granite Dam is located in the United States
Lower Granite Dam
Location in the United States
Lower Granite Dam is located in Washington (state)
Lower Granite Dam
Location in Washington
CountryUnited States
LocationGarfield and Whitman counties,
Washington
Coordinates46°39′38″N 117°25′41″W / 46.66056°N 117.42806°W / 46.66056; -117.42806
Construction beganJuly 1965
Opening dateJune 1975 (1975-06)[1]
Construction cost$624,098,663[2]
($3.21 billion in 2024[3])
Operator(s)U.S. Army
Corps of Engineers
Dam and spillways
Type of damGravity dam
ImpoundsSnake River
Height100 ft (30 m)
Length3,200 ft (980 m)
Spillway typeService, gate-controlled
Spillway capacity850,000 cu ft/s (24,000 m3/s)
Reservoir
CreatesLower Granite Lake
Total capacity440,200 acre⋅ft (0.543 km3)[4]
Surface area8,900 acres (36.0 km2)
Normal elevation741 ft (226 m)
TypeRun-of-the-river
Turbines6 × 135-155 MW units[5]
Installed capacity810 MW
Columbia River Basin
Columbia River Basin

Lower Granite Lock and Dam is a concrete gravity run-of-the-river dam in southeastern Washington in the United States. On the lower Snake River, it bridges Whitman and Garfield counties.[6] Opened 49 years ago in 1975,[1][7][8] the dam is located 22 miles (35 km) south of Colfax and 35 miles (56 km) north of Pomeroy.

Lower Granite Dam is part of the Columbia River Basin system of dams, built and operated by the U.S. Army Corps of Engineers; power generated is distributed by the Bonneville Power Administration (BPA).

Behind the dam, Lower Granite Lake extends 39 miles (63 km) east to the confluence with the Clearwater River at Lewiston, Idaho, and allowed the city to become a port.[1][9] The first barge to Portland on the 374-mile (602 km) navigation route was loaded with wheat and departed Lewiston on August 9, 1975.[10][11]

Lake Bryan, formed from Little Goose Dam, runs 37 miles (60 km) downstream from the base of the dam.

Construction

Construction began in July 1965,[12] but was halted less than two years later due to lack of funding.[13] Work restarted in 1970,[14] concrete was first poured in 1971,[15][16] and the main structure and three generators were completed in 1975, with dedication ceremonies on June 19.[1][7] An additional three generators were finished in May 1978,[17][18] bringing the generating capacity to 810 megawatts, with an overload capacity of 932 MW.

The spillway has eight gates and is 512 feet (156 m) in length. An 86-by-674-foot (26 by 205 m) navigation lock was also included in construction.[2]

Just downstream (northwest) of the dam on the east bank, Boyer Park was constructed by the Corps of Engineers and opened in April 1973.[19]

Fishery

Lower Granite Dam is the most upstream dam in the Snake River system that has a fish ladder to allow adult salmon and steelhead to migrate upstream. The Columbia River treaty tribes, along with some environmental groups, have recommended that this dam along with the other three lower Snake River dams be decommissioned and/or removed because of their impact on threatened and endangered chinook (threatened) and sockeye salmon (endangered) and steelhead (threatened) populations.,[20][21] The Corps of Engineers recognized in 1971 that the dam would have a detrimental impact on wildlife.[22]

A significant increase in the sockeye salmon return to the Columbia River in 2008 proved a pleasant surprise and raised hopes for increased salmon runs across the Lower Granite. Wildlife officials were not certain of the reason for the increased salmon return (Idaho Statesman, June 28, 2008). The Corps of Engineers has installed new devices, such as removable spillway weirs, in an attempt to make the dam less harmful to juvenile salmon.

There is also a juvenile bypass/collection facility that collects juvenile migrating salmon and steelhead so they can be transported downstream by barge.

  • Single-lift
  • Width: 86 feet (26 m)
  • Length: 674 feet (205 m)
Lower Granite Dam with the lock in the center, the power generation on the south side of the river (right side of the photo), and spillway in the middle of the dam, between the powerhouse and the lock.

Asotin Dam

Authorized by Congress in 1962,[23] a fifth dam on the lower Snake River was proposed several miles upstream (south) of Lewiston.[24] Concerns over its environmental and recreational impact stalled the Asotin Dam project,[25][26][27] and it was ultimately canceled in 1980.[28] The Asotin County public utilities district attempted to revive the project in 1988,[29] but it was quickly blocked by Congress,[30][31] and a law banning future dams was signed into law by President Reagan on November 17.[32][33]

Other proposed dams further upstream were not built either: the High Mountain Sheep Dam above the confluence with the Salmon River,[34] and the Nez Perce Dam, just below it.[24][35]

Road closed

Following the September 11 attacks in 2001, the road across the Lower Granite Dam was closed for over six years; it reopened for weekend traffic in May 2008.[36] The sand dune area downstream on the south shore (46°41′46″N 117°28′48″W / 46.696°N 117.48°W / 46.696; -117.48), accessed over the dam, was popular with local college students from Washington State University and the University of Idaho.[37]

See also

References

  1. 1 2 3 4 Harrell, Sylvia (June 20, 1975). "Dedication: Andrus brings a warning". Lewiston Morning Tribune. p. 1.
  2. 1 2 "LOWER GRANITE LOCK AND DAM--LOWER GRANITE LAKE". U.S. Army Corps of Engineers. Archived from the original on May 17, 2011. Retrieved July 17, 2010.
  3. 1634–1699: McCusker, J. J. (1997). How Much Is That in Real Money? A Historical Price Index for Use as a Deflator of Money Values in the Economy of the United States: Addenda et Corrigenda (PDF). American Antiquarian Society. 1700–1799: McCusker, J. J. (1992). How Much Is That in Real Money? A Historical Price Index for Use as a Deflator of Money Values in the Economy of the United States (PDF). American Antiquarian Society. 1800–present: Federal Reserve Bank of Minneapolis. "Consumer Price Index (estimate) 1800–". Retrieved May 28, 2023.
  4. "The Four Lower Snake River Dams". Bluefish.org. Retrieved July 17, 2010.
  5. "Lower Granite Dam". Washington.edu. Retrieved July 17, 2010.
  6. "The Columbia River System Inside Story" (PDF). BPA.gov. pp. 14–15. Archived from the original (PDF) on May 27, 2010. Retrieved July 17, 2010.
  7. 1 2 Bunning, Paul (June 20, 1975). "Andrus salutes dam project". Spokesman-Review. p. 6.
  8. Dullenty, Jim (June 19, 1975). "Idaho's link to the sea is acclaimed by Andrus". Spokane Daily Chronicle. p. 1.
  9. "Snake River link to sea nearly complete". Ellensburg Daily Record. UPI. March 6, 1975. p. 3.
  10. "First wheat heads downriver". Lewiston Morning Tribune. August 10, 1975. p. 10A.
  11. "Grain barge nears Portland". Ellensburg Daily Record. UPI. August 11, 1975. p. 10.
  12. "Lower Granite Dam". Lewiston Morning Tribune. (photo). November 20, 1966. p. 6.
  13. "Engineers award contract for Lower Granite Dam". Lewiston Morning Tribune. May 14, 1970. p. 16.
  14. Roskelley, Fenton (December 8, 1969). "Dam construction halt is sought". Spokane Daily Chronicle. p. 19.
  15. Pierce, Virginia (February 27, 1971). "Concrete pouring phase is begun at Lower Granite Dam site". Spokane Daily Chronicle. p. 5.
  16. Harrell, Sylvia (February 27, 1971). "Work on dam to continue despite shortage of funds". Lewiston Morning Tribune. p. 18.
  17. "Lower Granite power complex complete". Lewiston Morning Tribune. May 13, 1978. p. 6A.
  18. "Lower Granite Dam powerhouse finished". Spokane Daily Chronicle. May 16, 1978. p. 15.
  19. "Boyer Park open to public". Spokane Daily Chronicle. April 7, 1973. p. 12.
  20. "Dams and Salmon - Decommissioning Dams - Hydropower Dams". Archived from the original on July 23, 2011. Retrieved May 2, 2011.
  21. "5-Year Review: Summary & Evaluation of Snake River Sockeye, Snake River Spring-Summer Chinook, Snake River Fall-Run Chinook, Snake River Basin Steelhead" (PDF). National Oceanic and Atmospheric Administration. 2011. Retrieved December 3, 2013.
  22. "Lower Snake dam called detrimental to wildlife". Spokesman-Review. Associated Press. November 23, 1971. p. 8.
  23. "Asotin Dam plan funds endorsed". Spokesman-Review. September 28, 1967. p. 6.
  24. 1 2 Hewlett, Frank (February 6, 1964). "High Mountain Sheep Dam project approved". Spokesman-Review. p. 1.
  25. "Asotin Dam criticized". Spokane Daily Chronicle. December 19, 1969. p. 19.
  26. "Luders heads drive to halt funds for dam". Spokane Daily Chronicle. March 12, 1973. p. 6.
  27. "Symms bill would halt Asotin Dam". Spokane Daily Chronicle. Associated Press. March 14, 1973. p. 3.
  28. "Consortium ends Asotin Dam idea". Spokane Daily Chronicle. Associated Press. August 27, 1980. p. 5.
  29. "Asotin Co. dam idea studied". Idahonian. Associated Press. June 17, 1988. p. 5A.
  30. "Senate passes Idaho dam ban". Spokane Chronicle. Associated. August 12, 1988. p. 9.
  31. Trillhaase, Marty (August 12, 1988). "McClure wins halt to Snake, Salmon dams". Lewiston Morning Tribune. p. 1A.
  32. Loftus, Bill (November 18, 1988). "Federal law bans proposed dam at Asotin". Lewiston Morning Tribune. p. 1A.
  33. "Bill will guarantee free-flowing Snake". Spokane Chronicle. wire reports. November 18, 1988. p. A2.
  34. "High Mountain Sheep Dam will rise in rugged land". Spokesman-Review. February 26, 1964. p. 20.
  35. "Dam dispute due in court". Spokesman-Review. Associated Press. January 29, 1967. p. 25.
  36. Rokyta, Devin (May 17, 2008). "Weekend crossings are again allowed at Lower Granite Dam". Moscow-Pullman Daily News. p. 1A.
  37. "Staying for the summer". Gem of the Mountains, University of Idaho yearbook. 1987. p. 71.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.